I can successfully use process builder to create tasks. I have one currently setup that looks at a date field and then creates a task 7 days later. So no problem there.
There is a field called Project time. This is a number. For example 180 (days). Is it at all possible for Process Builder to look at this field in my my example and create a task 90 days later? (which is halfway) Is there any kind of formula that can look at a number field and halve it?
We have varying project lengths hence needing a formula that will be able to take any number and halve it.
Any ideas at all people? :)
-thanks,
Lewis
1 answer
Hi Lewis,
You will need to do the belowCreate a formula field on the object and the formula will be
TODAY() + FLOOR(Project_time__c/2)
now on the process builder
create a schedule and the schedule will 0 Days After formula Date field