Hi All,
We are facing some issues with using Snapshots to create Scratch orgs with pre-installed managed packages.
We use a base Scratch org to install all required managed packages, and we create a Snapshot out of it. Installed packages behaves fine as expected on the base Scratch org. However when we start creating Scratch orgs from a Snapshot, we notice an inconsistent behaviour.
On Scratch orgs created from Snapshot, we have noticed managed packages (Twilio as an example) having the "Status" as "Trial". Whereas on the base Scratch org it was "Free". I also tried re-installing the package manually, and the "Status" was "Free".
This inconsistent behaviour is causing issues on our current CI pipeline and delivery timelines.
It is much appreciated if you could shed some light here.
CC: @Rohit Mehta
Cheers !
Shermal
Hi @Nick Goldsmith , as discussed in support case 26495482, would you be able to assist Shermal on this please?