Hi All,

I had scheduled around 22 Jobs till last Friday on on SF Org with different schedules. All these 22 jobs were visible in Scheduled Jobs Tab. Starting from this Monday(16th Feb 2015) I'm getting an Error : System.AsyncException: You have exceeded the maximum number (5) of Apex scheduled jobs when I try to schedule the same number of Jobs.

Its allowing only 5 Jobs to be submitted. 

Org might have been upgraded to Spring 2015 over the weekend. As per the Spring 2015 notes, we can use Apex Flex Queues to shcedule upto 100 Apex Jobs. We tried activating the Apex Flex Queue from Critical Updates section, but still the issue persists.

Need advise on what can be done to get the limit back to 100.
30 个回答
  1. 2015年2月24日 13:51
    This issue affected an Enterprise Edition demo/test environment we had created from the Partner Portal.  Thanks to @Abhishek at Salesforce who responded to my case, the news is that this was due to a new limit of 5 imposed on Trial/Free Orgs from the time of the release.  Due to the impact caused by the change, that limitation will be removed in 1st week of March and we should see the ability to schedule up to 100 Apex Jobs restored in all types of Orgs where it was possible before.  Interested to know of any production Orgs affected as we have held back from a customer go-live while seeking updates on this.
0/9000