For teams that use scrum development methodology, when is the best time to conduct UAT? Is UAT a seperate story? Does it occur during a seperate sprint? In my world, developers are responsible for writing their own test classes but UAT is often missed. How do you all incorporate UAT testing into your development process? 

3 条评论
  1. 2017年3月10日 02:36
    Sorry to be contributing a little bit late, however in my experience - Scrum teams are often very development centric, and not as user focused. This isn't necessarily bad, you would need to ensure the subsequent sprint will have BA's or QA resources working with business users during UAT. This works well, assuming the BA / QA resources aren't overloaded with this extra work in the second sprint (as they likely also have Sprint 2 tasks to do, that support the rest of the team). It's often been the pattern for the projects I've run, and has generally been successful!