I have created one validation rule to add days to a date field by calculating difference between two dates.

 

 
2 respuestas
  1. 8 oct 2015, 17:05
    Kiran, 

     

    For calculating difference between two date, you can simply do:

    Date_Field1__c - Date_Field2__c

     

    Now , let's say you want to add the result (number) of above equation to a date field (let's call it Date_Field3__c), you will simply do:

    Date_Field3__c + (Date_Field1__c - Date_Field2__c)

     

    If you want to update an existing date field (Date_Field3__c), just use the above formula in the field update part of a workflow rule. If you want to create another field that stores the result, just create a new formula field of date type (let's call it Date_Field4__c) and use the second formula that I posted above.

     

     