Morning all!
Ok so I am working on a project to look at contract information. In the viz that I am creating I want to look at the amount of days left on a contract before the end date.
The issue that I am having is that the dataset has a contract award number but everything else in the dataset (including the start and end dates) have more than value for each contract award number. I don't know how to get down to just one start and stop date for a contract award number.
The best results have been achieved when, in my real project I have added MAX(END DT) and MIN(START DT) in a variety of places such a filter, rows, details. So if all I wanted to give was a representation of an Excel sheet I would be in business! NOT!
I have tried a LOD expression but seems that I can only fit either MAX(END DT) or MIN(START DT) to that expression. Additionally, in my real dataset, there is a version number so I have used a LOD expression to pull the MAX version number but the calculation seems to take such a LONG TIME!
I am wondering if any of you have any suggestions on where to go with this data.
Thank you,
Scott
PS - I am working with Tableau 10.5 and have attached a sample workbook with made up data.
Hi Scott,
You should be able to get the overall start/end dates using LoD calculations.
Example:
I did a similar calc for ContractEnd, using max(End Date). Then wrote a calc for contract length that subtracts the 2 and was able to get to this.
Is this what you are trying to accomplish? Hope it helps!
- Jim