If a case is assigned to a particular team then milestone starts for that team then when we assign it to some other team then this particular milestone should stop and new milestone for the new team should start, and then when user assigns back to the first team, then that team's milestone should resume from where it was left. #Milestones & Entitlement Management #ServiceCoud

2 respuestas
  1. 29 abr 2023, 10:51

    Hi Gauri, You can customize the logic to calculate remaining time.

    Create a Custom Object  which has look up to Case

    EX: Team Milestone. 

    Create required fields to capture  Case Details like Case id,  Team Name, Target Time, Time Spent on Case, IsActiveTeam(Boolean). 

    Whenever Case is assigned to  Team ex: Team A, Create a Record capturing all case details ensure to set  IsActiveTeam as true.

     

    The moment Case is assigned to Team B, 

    1) Calculate Team A's Time Spent on Case & set IsActiveTeam as false. 

    2) Create Record for Team B capturing all case details ensure to set  IsActiveTeam as true.

     

    Create a Entitlement Process & Milestone. Under milestone create  a apex class which returns the remaining time.

    Inside the Apex class : Query Custom Object record where  IsActiveTeam = true.

    calucate the remaining time by  TargetTime - Time Spent on Case and pass it to the milestone.

     

    Let me know if this works.