Our Current Setup (Production) : Single Node (2022.1.1) Old Version - VM Machine

To be Environment (Not yet productionized) : 3 Nodes - 2024.2.2 - New VM Machine.

 

To be Environment :

Started with Node1 - Procured new server and Installed 2024.2.2 Version.

Restored production backup and copied to new server, testing completed on Node1.

 

Option 1:

What is the best way to move further to add Node 2 and Node 3.

Should i add node 2 and 3 and restore backup again before cutover?

Will this work? Copying backup from single node(Old server) to new Environment?

 

Option 2 :

Release new server into production. Single node --> Single node cutover?

Then upgrade on one weekend to Node 2 and Node 3?

In this case no need to copy and restore the back up as this environment is already up to date?

 

Please suggest.

답변 11개
  1. 2024년 11월 8일 오전 10:15

    @krishnapriya Arisetti​ sorry if I wasn't explicit enough in my answer. you have done nothing wrong and there is nothing else you have to do with Tableau Server. Your IT team has to jump in and verify that your node 2 and node 3 have a functioning network connectivity to your SMTP server over port 25.

    If you continue to have specific issues with your Tableau Server cluster that you cannot solve, please create new forum topic so people can find a similar issue through forum title search and benefit from the resolution.

    ----------------------