Michele DeGabriele 님이 #Data Management에 질문했습니다
I have created a process in Process Builder that will update a checkbox on an Account when a Case of a certain type has a date within the last 90 days. It works fine but what happens is that when the date moves out of the last 90 days range the Account checkbox stays checked!

 

How do I get this to dynamically update? I know this has something to do with the "when a record is created or edited" limitations. Is there some way I can use the scheduled actions to make this happen?

 

 
답변 2개
  1. 2016년 2월 19일 오후 7:57
    Hi,

     

    You need to create on more time dependent action using process builder which will uncheck that field after 90 days from created date or modified date.

     

    Hope this helps !!

     

    --

     

    Thanks,

     

    Swayam