We want to add "pre-pipeline" with the status of "omitted". However, I get the error "duplicate status category". I'm assuming each status can only be tied to one category? Is there a workaround to this? We want pre-pipeline to also be omitted. 

1 risposta
  1. 23 ott 2024, 22:35

    Unfortunately, you are limited to only 5 Forecast Categories and each one must have a unique Status Category. You can rename the existing Omitted to Pre-Pipeline, but if you need both, the next best option is to create a new custom field that is either a Picklist populated by Flow or a Formula Field based on the Opportunity Stage.