Hi. Whenever I create a task, I need the due date to be automatically set to 30 days in the future. However, the date that is set must not be a weekend day.
I.e. I create the task on July 30. July 30 + 30 days would be August 29. August 29 is a Sunday. The formula within a process builder action needs to adjust the due date to August 30, which is a Monday.
Same idea if due date lands on a Saturday.
Would greatly appreciate any help.
Thanks,
답변 2개
Hi Emmanuel Grembo ,
You can refer: https://trailhead.salesforce.com/trailblazer-community/feed/0D54S00000A8tvLSAR
Similar issue has been mentioned on this link.
Hope this helps!